DARTFORD CROSSING CHANGES
Briefing Document
November 2014

Compiled by Paul Murphy-Kasp – November 2014
Correct as of 20th November 2014

CONTENTS

 What’s Happening
 Timetable & Roadwork’s
 ‘Dart Charge’

2

WHAT’S HAPPENING
From 6am on Sunday 30th November 2014, the toll booths at the QE2 Bridge / Dartford
Tunnels will no longer be used to collect payments to use the bridge/tunnels.

The Highways Agency have said that removing the toll booths and getting users to pay in
advance or by midnight the following day, will reduce congestion in the area and ease the
flow of traffic.

Although these changes take place from Sunday 30th November, works begin on Friday
28th November to remove the existing toll booths, reconfigure the road layout so that four
lanes will run in both directions, and new traffic control measures will be introduced for
restricted vehicles wanting to use the Dartford Tunnel. During these works there’ll be
temporary speed limits and lane restrictions, all of which will be clearly signed for drivers.

Traffic approaching the Dartford Tunnel (Northbound/Anticlockwise) will still see the use
of the existing toll barriers to stop restricted vehicles from accessing it. If using the QE2
Bridge (Southbound/Clockwise), barriers will be removed more quickly as there are fewer
restrictions for vehicles using the bridge.

3

TIMETABLE & ROADWORKS
Works will begin on Friday 28th November 2014 to remove the toll booths and adjust the
road layout. These works will finish in Spring 2015
During these works, there'll be:


Lane restrictions during the day on the approaching to the M25 J1A Roundabout

 Overnight lane and slip road closures as well as full closures
 Speed restrictions
Most of the large-scale works will take place early on, and are timetabled as follows

FRIDAY 28th NOVEMBER
Overnight works (2300-0600)
Down to a single lane on the QE2 Bridge (three lanes closed)
The M25 Clockwise entry slip road at J31 will also be closed
DIVERSION – To avoid the likely queues, use the A13 into London, the A12/A102 Blackwall
Tunnel, and then the A2 back to J2 of the M25

SATURDAY 29th NOVEMBER
Daytime works (0600-2200)
Clockwise - Four of the toll booths will be closed

SATURDAY 29th NOVEMBER
Overnight works (2200-0600)
Down to a single lane on the QE2 Bridge (three lanes closed), and both Dartford Tunnel
bores will be CLOSED
The M25 Clockwise entry slip road at J31 will also be closed
DIVERSION – To avoid the likely queues, use the A13 into London, the A12/A102 Blackwall
Tunnel, and then the A2 back to J2 of the M25 (and vice versa)

SUNDAY 30th NOVEMBER
Daytime works (0600-2200)
Clockwise - Four of the toll booths will be closed. Anticlockwise – Temporary road layout

4

SUNDAY 30th NOVEMBER
Overnight works (2330-0600)
Both the QE2 Bridge and Dartford Tunnel will be CLOSED
The M25 Clockwise entry slip road at J31 will also be closed
DIVERSION – To avoid the likely queues, use the A13 into London, the A12/A102 Blackwall
Tunnel, and then the A2 back to J2 of the M25 (and vice versa)

MONDAY 1st DECEMBER – UNTIL LATE DECEMBER
24 hours a day from 0600 on December 1st
Temporary road layout in place (both directions).

5

DART CHARGE
With the removal of the toll booths comes a new way of paying to use the QE2 Bridge and
Dartford tunnel. Similar to the Central London Congestion Charge, users will either be able
to pay in advance, or by midnight of the following day.
Drivers will be able to pay online, by phone, by post or at ‘payzone’ retail outlets. Another
option is that drivers can set up a Dart Charge pre-pay account which may offer discounts
of up to one-third for every crossing
If you already have a ‘DART-Tag’, then you will not need to set up an account as you will be
contacted on how to change to Dart Charge.
From Sunday 30th November, there’ll also be an increase in the charge to use the QE2
Bridge and Dartford Tunnel:

6






Download Dartford Crossing



Dartford Crossing.pdf (PDF, 495.46 KB)


Download PDF







Share this file on social networks



     





Link to this page



Permanent link

Use the permanent link to the download page to share your document on Facebook, Twitter, LinkedIn, or directly with a contact by e-Mail, Messenger, Whatsapp, Line..




Short link

Use the short link to share your document on Twitter or by text message (SMS)




HTML Code

Copy the following HTML code to share your document on a Website or Blog




QR Code to this page


QR Code link to PDF file Dartford Crossing.pdf






This file has been shared publicly by a user of PDF Archive.
Document ID: 0000196262.
Report illicit content